Cookie Consent by Free Privacy Policy Generator website
Housing

Rewiring council homes

If the wiring in your home is old, we will rewire it so that it is safe and meets the decent homes standard (Tenant's Choice).

How we rewire council homes

The existing sockets, switches and fuse board will be removed and we will fit a modern consumer unit (fuse board) and a hard-wired smoke alarm.

Sockets

New socket and switch positions will be agreed. Where possible, we will give you the choice of where you would like the sockets to be fitted. The number of sockets we fit in each room is shown below.

Room Sockets
Kitchen 3 double sockets and a cooker point. Single sockets and isolators for your appliances
Living room 4 double sockets
Bedrooms 2 double sockets
Hall and landing 1 double socket

Cables

Where possible new cables will be installed in the roof space, under the first floor and inside partitions. But if the walls are solid, we will need to cut into the wall to fit the cables and replaster.

Fuse board or consumer unit

We will install a new consumer unit. The new consumer unit will have switchable fuses and a very sensitive fault detection switch (Residual Current Device, or RCD).

The rewiring process

You will be informed in writing of the start date for the work in your area. Our approved contractor will carry out a first survey 2 weeks before the work is due. The contractor will carry out a second survey 7 days later and confirm the actual date to start work in your home.

If your home is being rewired only, then the work will be completed within 5 working days.

If the rewiring is part of the Tenant's Choice scheme the work will be completed within 3 working days but will be fitted in with the other work that takes place over 10 working days.

The contractor will need access to your home for up to a further 3 days to carry out a final inspection and complete any remedial work.

Preparing for rewiring in your council home

The contractor will call about a week before the work is due to start and explain what you need to do, this may include the following:

  • the new fuse board will probably be fitted in the same place as your existing one. If this is in a cupboard, empty it to allow easy access
  • safely store any electrical items such as televisions as well as ornaments to stop them being damaged accidentally
  • take down lampshades or remove glass shades from chandeliers. Chandeliers will be refitted provided they are properly earthed
  • the contractor will advise if you need to loosen or lift carpets
  • in upstairs rooms the contractor may need to lift floorboards to gain access to the lights below. This means you will have to lift upstairs carpets and move furnishings
  • if you have laminated flooring the contractor will look at alternative cable routes to avoid the need to lift it. If this is not possible you will need to lift the flooring; we will discuss this with you before starting work
  • we will need to get into your loft. If your loft has been boarded these boards will need to be lifted. Stored items may need to be moved to gain access to the lights below

Disruption during rewiring

Unfortunately, when your home is rewired every room is affected. We aim to keep disruption to a minimum so you will only be without power for a few hours.

As most heating systems rely on electrical controls, there will also be minor interruption to your heating and hot water supply.

The contractor will treat you and your home with courtesy and respect. They will use dust sheets, clean up any mess and pack away tools and materials at the end of each day.

The most disruptive work takes place in the first few days, which might involve cutting channels in the wall for new sockets.

You will be able to stay at home during the work. The dust, noise and general upheaval may cause you some discomfort so you may decide to spend some time away from your home.

The contractor will follow safe working practices. You should follow any advice they give you. This is because there will be hazards such as building materials on the floor, lifted floorboards and equipment being used by the contractors.

You will have a fully working electrical system at the end of the first day but work will take up to 5 days to complete.

Once wiring installation is complete any minor work such as replacing skirting boards and tidying up will take place.

Decoration after rewiring

We are unable to cover the cost of redecoration, but you will receive a decoration pack which includes:

  • emulsion and gloss paint
  • polycell filler
  • a roller and tray
  • paint brush pack
  • masking tape
  • a dust sheet
  • decorators caulk
  • sandpaper

If you have any queries, contact the Capital Projects team.

Also see

Housing Capital Projects Team

Please contact the Housing Capital Projects Team by email, other than in an emergency or if you don't have access to email.

Eco Depot, Hazel Court, York, YO10 3DS

Telephone: 01904 551550