We control aspects of building (or structure) demolition within our area, except when buildings are exempt from such control.
Read about:
- buildings exempt from demolition control
- demolishing a building
- starting demolition work
- demolishing listed buildings and buildings in conservation areas
- health and safety when demolishing a building
- asbestos and demolition
Buildings exempt from demolition control
Buildings exempt from demolition control are:
- buildings having an external size of less than 50 cubic metres (less than the average double garage)
- extensions on a larger building that consists of an attached conservatory, shed or garage
- buildings used solely as agricultural buildings
- work in occupied buildings where it is intended that it should continue to be occupied
Demolishing a building
If you intend to demolish a building or structure that is not exempt you should give notice to our Building Control Team before any demolition work starts.
The notice must be in writing and must specify the building to be demolished. A copy of the notice should also be sent to or given to the following:
- the occupiers of any building adjacent to the building to be demolished
- Work Scheduling Station, British Gas
- The electricity supplier
- Yorkshire Water
When we receive a notification that you intend to demolish a building we can respond by 'serving a counter notice' (section 81 notice) which sets out conditions that must be met during the course of demolition.
Starting demolition work
Demolition work should only start after either:
- we have served a counter notice, under section 81 of the Building Act 1984
- a period of 6 weeks has passed since we received your written notification
Demolishing listed buildings and buildings in conservation areas
Any alteration of a listed building involving partial or complete demolition requires formal listed building consent. Unauthorised alteration is illegal and can result in prosecution.
The substantial or complete demolition of an unlisted building in a conservation area requires listed building consent.
Get advice from our Conservation Officers on whether your proposals need formal permission.
Health and safety when demolishing a building
for Visit the Health and Safety Executive website for advice about Construction Design and Management Regulations which apply to most demolition work.
Asbestos and demolition
If you find asbestos containing materials during demolition work you must notify the Health and Safety Executive immediately, and follow their requirements for safe removal and disposal.
Unless a skip operator or other contractor is already licensed to transport asbestos based products, a licence will be required from the Environment Agency to move any asbestos based material off site.